Industrial Developments Construction Stages Methodology
Industrial project durations vary widely depending on scale and complexity. For instance, a 50,000 square foot assembly plant may take around a year to complete, while a semiconductor facility exceeding 500,000 square feet can span more than three years. To ensure consistent progress tracking across these different project types, Aterio applies a percentage-based timeline framework that represents proportional completion milestones rather than fixed durations.
Percentage Framework
Construction milestones are assigned to key progress intervals (e.g., 5%, 10%, 20%). These percentages indicate visible, externally verifiable progress observed through satellite imagery. All timelines account for the reality that interior work constitutes a significant portion of total construction time but remains invisible to satellite monitoring.
Visual Indicators Used for Progress Assessment
Aterio’s analysts measure construction progress using consistent, visible cues in imagery, including:
Surface transitions – from vegetation to graded soil to finished surfaces
Structural evolution – framing, roofing, and building footprint expansion
Equipment and exterior installation – generators, rooftop units
Site completion work – paving, landscaping, or boundary development
Aterio’s Percentages Framework for Industrial Development
5% - Site Clearing Initiated
Visible: Color change from green/existing to brown/disturbed soil
Indicators: Site boundaries visible, vegetation removed, earth disturbance patterns
10% - Land Grading and Leveling
Visible: Uniform earth tone, grading patterns, equipment tracks
Indicators: Smooth surface, visible grading contours, drainage features
20% - Foundation Excavation Visible
Visible: Dark trenches/holes, stockpiles at perimeter
Indicators: Excavation shadows, foundation perimeter defined, soil pile formations
30% - Foundation Concrete Poured
Visible: Light gray concrete patterns, rectangular foundation footprint
Indicators: Concrete surface texture, defined building outline, uniform gray surface
40% - Structural Steel Erection Begins
Visible: Shadow-casting vertical elements, steel framework visible
Indicators: Vertical columns creating shadows, grid pattern emerging, height development
50% - Structural Steel Framing Complete
Visible: Building height evident, structural grid clear
Indicators: Multiple column rows visible, significant shadow casting, building form evident
60% - Roof Structure Begins
Visible: Mixed roof colors (completed vs in-progress sections)
Indicators: Partial roof coverage, color/texture variations, installation pattern visible
70% - Roof Installation Complete
Visible: Uniform roof color/texture across entire footprint
Indicators: Complete roof coverage, consistent surface appearance, no open areas
80% - Building Envelope Complete
Visible: No open bays, uniform building appearance, complete enclosure
Indicators: All exterior walls finished, doors/windows installed, weather-tight structure
90% - Exterior Equipment Pads Visible; Rooftop HVAC Units
Visible: Rooftop equipment visible, exterior pads/platforms present
Indicators: HVAC units on roof, transformer pads, exterior mechanical equipment
95% - Site Work and Paving Complete
Visible: Gray/black paved surfaces, parking stripes, loading areas
Indicators: Parking lots finished, access roads paved, line striping visible
100% - Landscaping and Final Site Improvements
Visible: Clean site, no staging areas/construction equipment, green spaces, defined pathways
Indicators: No visible construction activity, walkways completed, perimeter finished
Estimated Activation Dates
Aterio records the activation or completion date provided directly by the project developer or operator. When such information is not disclosed, activation dates are estimated using standardized construction duration benchmarks to maintain consistency across the dataset. These benchmarks align with typical timelines for large-scale industrial projects and are applied to ensure comparability between industry sectors.
Manufacturing Facilities Construction Timeline
Manufacturing facilities represent complex industrial builds due to specialized equipment requirements, utility needs, and process-specific infrastructure.
Timeline by Size
Small Facility (<50,000 sq ft): 10–14 months total construction
Medium Facility (50,000 – 150,000 sq ft): 18–24 months total construction
Large Facility (150,000+ sq ft): 36–48 months total construction
Warehouse Construction Timeline
Warehouses typically have faster construction timelines due to simpler building systems and standardized designs.
Timeline by Size
Small Facility (<50,000 sq ft): 6–9 months total construction
Medium Facility (50,000 – 150,000 sq ft): 12–16 months total construction
Large Facility (150,000+ sq ft): 22–30 months total construction
Solar Farm Construction Timeline
Solar farms have unique construction characteristics with significant equipment installation phases and weather dependencies.
Timeline by Size
Small Facility (<10 MW, <100 acres): 7–10 months total construction
Medium Facility (10–50 MW, 100–500 acres): 18–24 months total construction
Large Facility (50+ MW, 500+ acres): 30–42 months total construction
Energy Projects (Power Plants) Construction Timeline
Power plant construction involves extensive mechanical systems, long-lead equipment, and rigorous safety/environmental requirements.
Timeline by Size
Small Facility (<250 MW): 30–48 months total construction
Medium Facility (250–800 MW): 50–72 months total construction
Large Facility (800+ MW, incl. nuclear): 70–96+ months total construction
Hospitals Construction Timeline
Hospital construction is among the most complex due to stringent codes, specialized systems, and operational requirements during construction.
Timeline by Size
Small Facility (<100 beds, <100,000 sq ft): 40–54 months total construction
Medium Facility (100–400 beds, 100,000–350,000 sq ft): 60–84 months total construction
Large Facility (400+ beds, 350,000+ sq ft): 100–120 months total construction
Other Projects incl. Stadiums, Sports Facilities etc. Construction Timeline
These large-scale venues are unique mega projects combining complex structural, architectural, and mechanical systems with large occupancies.
Timeline by Size
Small Facility (<30,000 seats / <100,000 sq ft): 18–24 months total construction
Medium Facility (30,000 – 60,000 seats / 100,000 – 300,000 sq ft): 24–36 months total construction
Large Facility (60,000+ seats / 300,000+ sq ft): 36–48+ months total construction